<<Prev Rule

Texas Administrative Code

Next Rule>>
TITLE 43TRANSPORTATION
PART 1TEXAS DEPARTMENT OF TRANSPORTATION
CHAPTER 2ENVIRONMENTAL REVIEW OF TRANSPORTATION PROJECTS
SUBCHAPTER CENVIRONMENTAL REVIEW PROCESS FOR HIGHWAY PROJECTS
RULE §2.44Project Scope

(a) Project scope required. The project sponsor, in collaboration with the department delegate, will prepare a detailed project scope that describes the preparation of the environmental review document or CE/BCE/PCE documentation and performance of related tasks. A district, region, or division that has dual roles as both project sponsor and department delegate satisfies this requirement by placing the project scope in the project file. For purposes of this section, a project sponsor includes a local government that proposes to serve as a project sponsor and intends to seek the department's approval of such a designation under §2.47 of this subchapter (relating to Approval of Local Government as Project Sponsor).

(b) Form. The project scope must be prepared using a standardized checklist approved by the department that reflects the requirements of subsection (c) of this section.

(c) Content. The project scope must include:

  (1) a description of the project, including characteristics relevant to environmental review;

  (2) issues that must be addressed in the environmental review document for the project;

  (3) a statement of the anticipated classification of the project under Subchapter D of this chapter (relating to Requirements for Classes of Projects);

  (4) identification of the department delegate, including the department employee with authority to issue approvals under this chapter on behalf of the department delegate;

  (5) the name and contact information for the persons to whom communications between the project sponsor and department delegate should be addressed;

  (6) obligations to coordinate with participating agencies;

  (7) planned surveys or studies, including a description of additional tasks that may be required pending the results of such surveys or studies;

  (8) planned public participation;

  (9) a list of state and federal approval authorities;

  (10) a list of permits anticipated for the project;

  (11) any other tasks that the department delegate and project sponsor jointly determine must be undertaken by the project sponsor, including tasks that must be completed before submission of the environmental review document or CE/BCE/PCE documentation and tasks that must be completed later;

  (12) a plan showing the stages and persons responsible for engaging in informal dispute resolution under §2.52(a) of this subchapter (relating to Dispute Resolution Process) if a dispute arises concerning the preparation or review of the environmental review document or CE/BCE/PCE documentation, with a deadline for completing each stage of informal dispute resolution;

  (13) a schedule that shows when the project sponsor, or the department delegate if it agrees to perform specified tasks, will submit any environmental reports under §2.45 of this subchapter (relating to Optional Early Submittal of Environmental Reports), conduct coordination with participating agencies, conduct public participation, submit the environmental review document or CE/BCE/PCE documentation for the department delegate's review, and perform any other tasks outlined in the project scope; and

  (14) calculation of an optional fee in accordance with §2.46 of this subchapter (relating to Optional Payment of Fee by Local Government), if requested by a local government sponsor.

(d) Optional agreement between project sponsor and department. Notwithstanding any provision of this subchapter, the project scope may include the department delegate's agreement to complete a task that §2.43 of this subchapter (relating to Project Sponsor Responsibilities) otherwise directs is the responsibility of the project sponsor. Any such agreement must clearly identify the task that the department delegate has agreed to complete.

(e) Participation by FHWA. For a highway project for which an environmental decision requires FHWA approval, the FHWA may also be a party to the project scope. The project sponsor and department delegate will determine whether to invite FHWA to be a party to the project scope as soon as possible, but in no event later than the initial meeting between the project sponsor and the department delegate as provided for in subsection (f) of this section. Any matter agreed to by the project sponsor and the department delegate in the project scope, including the anticipated classification, may be subject to FHWA approval for an FHWA transportation project.

(f) Collaboration on preparation; deadline for issuing classification letter.

  (1) The project sponsor and department delegate will meet to discuss the preparation of the project scope not later than the 30th day after the date that the project sponsor submits its proposed project scope to the department delegate, unless before the end of the 30-day period, the department delegate and project sponsor agree that there is no need to meet to finalize the project scope or agree to meet at a specified later date.

  (2) If the project sponsor and department delegate do not agree on the project scope, the department delegate will complete a proposed project scope not later than the 60th day after the date that the project sponsor submits its proposed project scope to the department delegate.

  (3) For projects for which a local government proposes to be the project sponsor, the department delegate will issue to the local government on or before the 30th day after the date that the local government submits its proposed project scope to the department delegate, a letter indicating the anticipated classification of the project based on the information provided by the local government. If the department delegate indicates its approval of the project scope by signing it on or before the 30th day after the date that the local government submits its proposed project scope to the department delegate, a separate classification letter is not required.

  (4) The project sponsor and the department delegate will resolve any disagreements regarding the project scope, using the process set forth in §2.52 of this subchapter, before the deadline set forth in subsection (h) of this section.

(g) Receipt of optional fee. If the project sponsor is a local government that proposes to pay an optional fee under §2.46 of this subchapter, the fee must be received by the department before the department delegate may indicate its approval of the project scope by signing it.

(h) Deadline for agreed upon project scope. The project scope must be prepared and agreed to in writing by the project sponsor and the department delegate before the project sponsor submits an environmental review document or CE/BCE/PCE documentation to the department delegate for its review.

(i) Amendment of project scope. The project sponsor shall promptly notify the department delegate of any change in the description of the project. If, after completion of the project scope, there is a material change in the description of the project, or any other change that materially affects how the project sponsor will satisfy the requirements of this chapter, the project scope must be amended accordingly. An amendment must be agreed to in writing by the project sponsor and the department delegate.


Source Note: The provisions of this §2.44 adopted to be effective April 16, 2012, 37 TexReg 1727

Next Page Previous Page



Home TxReg TAC OM NewTac Public Footer Bar