| (a) Inspector Registration Fees.
(1) Original application--$50
(2) Renewal application--$50
(3) Revised/Duplicate registration card--$25
(b) Certificate of Compliance Filing Fees.
(1) Filing fees submitted within 60 days of the equipment
inspection date: $20 per unit of equipment, along with a copy of the
inspection report.
(2) Late filing fees: $10 per unit of equipment for
every 30 day period if the inspection report, filing fees, and verification
about correcting deficiencies in the inspection report are filed after
the 90th day from the equipment inspection date.
(3) Revised/Duplicate Certificate Fee--$25 per certificate
(c) Waiver or Delay Application Fees.
(1) $50 for each violation of the ASME Safety Codes
or ASCE Standards as adopted in §74.100 per unit of equipment
requested to be waived or delayed.
(2) Fees shall be charged and collected by the department
for a waiver or delay application for an institution of higher education.
(d) Contractor Registration Fees.
(1) Original application--$115
(2) Renewal application--$115
(3) Revised/Duplicate registration card--$25
(e) Department Fees, Travel and Per Diem.
(1) The fee for department personnel to disconnect
power or lockout equipment in a building shall be $200 per hour.
(2) The fee for department personnel to reconnect power
or unlock equipment in a building shall be $200 per hour.
(3) Travel and per diem costs shall be reimbursed by
the building owner in accordance with the current rate as established
in the current Appropriations Act.
(4) The department shall present a billing statement
to the building owner or representative after disconnecting the power
or lockout that is payable upon receipt unless the department receives
in writing verification that the expenses would be paid no later that
the 10th day after the date power is reconnected or equipment is unlocked.
(f) Late renewal fees for Inspector and Contractor
registrations issued under this chapter are provided under §60.83
of this title (relating to Late Renewal Fees).
(g) New Technology Variance Fees.
(1) Application fee--$2,500
(2) Fee to file an appeal of a denial of an application--$200
(h) Fees for Plan Reviews.
(1) The plan review fee for the installation or alteration
of equipment included in a contract shall be calculated as follows:
(A) $200 for each unit of equipment for which a decal
is required; and
(B) the maximum fee shall not exceed $5,000.
(2) The fee to review plans on an expedited basis is
$1,000 per unit of equipment included in a contract for which a decal
is required. There is no maximum fee or cap for expedited reviews.
(i) Fees for Amendments to Previously Approved Plan
Reviews.
(1) The plan review fee for amendments to previously
approved plan reviews where the installation or alteration of equipment
included in a contract has not been completed shall be as follows:
(A) $100 per unit of equipment for which a decal is
required; and
(B) the maximum fee shall not exceed $2,500.
(2) The fee to review amendments to previously approved
plan reviews on an expedited basis is $1,000 per unit of equipment
included in a contract for which a decal is required. There is no
maximum fee or cap for expedited reviews.
|