| (a) Within each fiscal year, a contractor may transfer funds between direct cost line items in different approved budget categories, not to exceed a cumulative total of ten percent of the approved contract budget during that year, without requesting a contract adjustment from the OAG. (b) If it becomes necessary to move funds that are greater than ten percent of the total budget between existing budget categories, revise the scope or target of the contract, add new budget categories, or alter contract activities, a contractor must first request and receive approval from the OAG for a contract amendment. (c) The OAG will allow only one contract amendment per state fiscal year unless: (1) the contractor demonstrates circumstances that the OAG deems adequately extenuating; or (2) the OAG requests the contract adjustment. |